Current Construction

Construction of 8-Inch Water Main On the 2400-2500 Blocks Of Janet Lee Dr. and 4300 Block Of Rosemont Ave., Project E-1008

(June 18, 2021)

Construction is complete on the 2400-2500 Blocks of Janet Lee Drive

 

Construction is complete on the 4300 Blocks of Rosemont Ave. Concrete restoration along the parkways will begin on June 21, 2021.

Construction of 8-inch Water Main on the 2800 blocks of El Caminito St., 4800 block of Dyer St., 4800 block of Glenwood Ave., and the 2700 block of Paraiso Wy., Project E-1022.

(June 18, 2021)

 

On May 20, 2021, Robert Brkich Construction broke ground on the 2800 block of El Caminito Street, 4800 block of Glenwood Avenue, 4800 block of Dyer Avenue, and the 2800 block of Stevens Street. The project will replace approximately 1,925 feet of old 4-inch water main and an additional 210 feet of old 2-inch water main on the 2700 block of Paraiso Way. The project aims to replace undersized aging pipes and provide improvements such as new 8-inch water mains, water services, valves, and fire hydrants. 

 

Excavation on the 2800 block of El Caminito Street began on Tuesday, June 8, 2021, with intermittent lane closures while the Contractor installed the new water main. Excavation is scheduled through June, along with traffic restrictions. The Contractor will post temporary "No Parking" signs a minimum of two (2) days before construction. Driveways within the work area may be temporarily restricted due to construction. CVWD's on-site inspector and the Contractor will assist you with access into and out of your driveway. 

 

Working hours are 7:30 am to 4:00 pm, although this can vary due to preparation time and individual project circumstances. Typically, construction work completed during a regular eight-hour shift will be paved and ready for traffic by the end of the shift. 

 

 The current project schedule is between June and September 2021.

Rehabilitation of Rosemont Reservoir, Project E-1018 

(June 18, 2021)

Construction is complete. 

Construction of 8-Inch Water Main On the 3400 and 3500 Blocks of Encinal Ave, Project No. E-1021

(June 18, 2021)

Construction is complete.